Energy
Following our mission and strategy we have established as one of the leading companies in Macedonia for modernisation of the energy MV/HV network. Our company is one of the main contractor for realisation of such projets in the distribution and trannsport grid.
Our successfull stories:
Supply of Digital Protection Relays for Feeder Bays and Transformer Bays for Medium Voltage Networks (35, 20, 10 kV) for the Needs of Elektrodistribucija
Procurement and delivery. Contracting Authority: Elektrodistribucija DOOEL Address: Lazar Lichenoski St. No.11, 1000 Skopje Equipment:• Facility: Butel Warehouse – Skopje• Product: Relays Year: 2024 –
Supply of Digital Protection Relays for Feeder Bays and Transformer Bays for Medium Voltage Networks (35, 20, 10 kV) for the Needs of EVN Macedonia
Procurement and delivery. Contracting Authority: EVN Macedonia AD Skopje Address: Lazar Lichenoski St. No.11, 1000 Skopje Equipment:• Facility: Butel Warehouse – Skopje• Product: Relays Year:
Electrical Installation Works for Automatic Voltage Regulation for ETR 1 at SS 35/10kV Vinica and ETR 2 at SS 35/10kV Balvan
Preparation of design documentation, procurement of equipment, AC/DC distribution, outfitting of bays. Contracting Authority: EVN Macedonia AD Skopje Address: Lazar Lichenoski St. No.11, 1000 Skopje
Expansion of SS 110/35/10 kV Negotino with a Second Transformer Bay
Procurement of equipment and reconstruction of the substation with construction of a second transformer bay. Contracting Authority: EVN Macedonia AD Skopje Address: Lazar Lichenoski St.
Replacement of 110kV Metering CTs with Combined Transformers at SS 110/35 kV Prilep 3 and SS 110/10kV Kavadarci 2 Gradska
Preparation of design documentation, procurement of equipment, dismantling of old and installation of new transformers. Contracting Authority: EVN Macedonia AD Skopje Address: Lazar Lichenoski St.
Automatic Voltage Regulation ETR 1 and 2 at SS 110/35/10 kV Kochani
Preparation of design documentation, procurement of equipment, automatic voltage regulation. Contracting Authority: EVN Macedonia AD Skopje Address: Lazar Lichenoski St. No.11, 1000 Skopje Year: 2024