SS 110/35/10 KV West-Skopje

Equipping a third 110 kV transformer field in SS 110/35/10 KV West-Skopje

Project design and implementation of complete primary and secondary equipment for a third 110 kV transformer field in SS 110/35/10 KV West-Skopje. Installation of 110KVA Circuit breaker, Installation of 2x 110KVA Disconector, Installation of 3x110KV Current measurement transformer. Design and manufacturing of cabinet for control and alarm signalization, cabinet for automatic voltage regulation, cabinet for protection, cabinet for remote signal concentration, cabinet for AC distribution, cabinet for DC distribution. Primary and secondary equipment connection.

2014, EVN Macedonia AD Skopje